CVEC Fiber

View Original

Why does fiber take so long?

Sign up to our Connected-Community to get all the latest information on CVEC Fiber and when we’ll be in your neighborhood!

To see the answers to the Connected Community's questions on this video, head to the following Q&A video.

  • Planning phase with survey crews and contractors doing pole examinations.

  • Check if there is any preparation necessary for placing the fiber on the poles.

  • Change out poles that need changing.

  • Getting any tree trimming taken care of.

  • Steel cables hung on poles as supporting structure.

  • Fiber lines are hung from the steel cables.

  • Splicing begins on the fiber lines that have been hung on the poles to create a continuous line.

  • This is when we are building fiber to your premises.

  • We will be contacting the areas about a month out from this point to start scheduling installations!

  • We splice the fiber from your premises to the fiber cables on the poles.

  • Our installers set up your home equipment and get light running into your premises!

  • Enjoyment of the fastest most reliable internet begins!